Liquidated Damages after Termination of Contract: Termination of LDs or just Termination of the Contract? April 25, 2019 Construction law practitioners are familiar with the Singapore case of LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd [2011] SGHC 163 (LW Infrastructure). The Singapore High Court in that case held that in the absence of express provision to the contrary, termination of the contract does not affect a claim for liquidated damages in respect of the period before termination. This case is also cited with approval in Law and Practice of Construction Contracts, 5th edition (Sweet & Maxwell 2018). For all intents and purposes, the Singapore law position appears settled even though there is no direct guidance from the Singapore Court of Appeal.