“2.32.1 If the Trade Contractor fails to complete the Works or works in a Section by the relevant Date for Completion of a Section or the Works, the Employer may, not later than 5 days before the final date for payment of the amount payable under clause 4.16, given notice to the Trade Contractor which shall state that for the period between the relevant Date for Completion of a Section or the Works and the date of practical completion of the Works or Section that:
2.32.1.1 he requires the Trade Contractor to pay liquidated damages at the rate stated in the Trade Contractor Particulars, or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; and/or
2.32.1.2 that he will withhold or deduct liquidated damages at the rate stated in the Trade Contract Particulars, or at such lesser stated rate, from sums due to the Trade Contractor.
2.32.2 If the Employer intends to withhold or deduct all or any of the liquidated damages payable, an appropriate Pay Less Notice must be given by or on behalf of the Employer.
…
“The following rates of liquidated damages will apply for the first 4 weeks (inclusive) of delay in completion of the Works beyond the Date for Completion:
• £nil per week or pro rata for part of a week.
Liquidated damages will apply thereafter at the rate of £25,000 per week (or pro rata for part of a week) up to an aggregate maximum of 7% of the final Trade Contract Sum …'”